Â鶹´«Ã½

Louis Dreyfus Maintenance Work - 2021

ProjectLouis Dreyfus Maintenance Work - 2021
Date08-16-21 to 09-17-21
LocationTerminal 86 - Seattle, WA

Project Summary

The work for this project included replacing grain spout pipes, boom tip pins and sheaves, support spout rollers and boom wires. The crane utilized on this project was the Guardian.