Â鶹´«Ã½

Washington United Terminal (WUT) Fender Concrete Piling Repair

ProjectWashington United Terminal (WUT) Fender Concrete Piling Repair
DateOct 12-17, 2019
LocationWUT Dock, Tacoma, WA
Contract$600,000

Project Summary

Remove and replace the two (2) damaged concrete fender piles at WUT.  Reinstall fender system unit after pile replacement.  Work completed within the Port of Tacoma Pier & Marine Repair On-Call 2019 contract.

 
John Woodward, Piledriving Foreman and Venon Uy, Project Superintendent
John Woodward, Piledriving Foreman and Venon Uy, Project Superintendent